Construction Milestones

Phase I

1 st Met Mast Construction Completed


2015/08/11

Sea Cable Arrived Taiwan

2016/03/16

Gets the Offshore Wind Turbine Construction Permit


2016/03/31

Torban Jack-UP Vessel Torban Arrived Taiwan


2016/06/11

Wind Turbine Arrived Taiwan


2016/06/20

1 st Two Offshore Wind Foundation Installation Start


2016/06/20

1 st Two Offshore Wind Foundation Installation Completed


2016/09/25

Subsea Cable Laying Completed


2016/10/21

1 st Two Offshore Wind Turbines Installation Completed


2016/10/27

Gets the Taiwan first offshore wind power license

2017/04/28

Phase II

Gets the Establishment Permit

2018/02/05

Gets the Sea Cable Laying Permit


2018/08/17

Gets the Offshore Wind Turbine Construction Permit

2018/11/26

Blades Arrived Taiwan

2019/03/31

Foundation installation Vessel Yudin Arrived Taiwan

2019/05/01

WTG installation Vessel Zaratan Arrived Taiwan

2019/05/15

Sea Cable Arrived Taiwan

2019/05/30

Offshore Wind Foundation Installation Start

2019/06/01