Construction Milestones
Phase I
1 st Met Mast Construction Completed
2015/08/11
Sea Cable Arrived Taiwan
2016/03/16
Gets the Offshore Wind Turbine Construction Permit
2016/03/31
Torban Jack-UP Vessel Torban Arrived Taiwan
2016/06/11
Wind Turbine Arrived Taiwan
2016/06/20
1 st Two Offshore Wind Foundation Installation Start
2016/06/20
1 st Two Offshore Wind Foundation Installation Completed
2016/09/25
Subsea Cable Laying Completed
2016/10/21
1 st Two Offshore Wind Turbines Installation Completed
2016/10/27
Gets the Taiwan first offshore wind power license
2017/04/28
Phase II
Gets the Establishment Permit
2018/02/05
Gets the Sea Cable Laying Permit
2018/08/17
Gets the Offshore Wind Turbine Construction Permit
2018/11/26
Blades Arrived Taiwan
2019/03/31
Foundation installation Vessel Yudin Arrived Taiwan
2019/05/01
WTG installation Vessel Zaratan Arrived Taiwan
2019/05/15
Sea Cable Arrived Taiwan
2019/05/30
Offshore Wind Foundation Installation Start
2019/06/01