The total installation capacity of Formosa I is 128MW; the first phase commissioned in 2017 having a capacity of 8MW; the second phase, to be completed in 2019 will have capacity of 120MW.
News
-
The Arrival of Turbine Blades and Towers for the Second Phase of the Formosa I Project
- 2019-04-18
- 發佈: ftdadmin
- Category: Newsletter
無迴響The second phase 120 MW facility in the Formosa I project is expected to be completed at the end of 2019. Currently, the wind turbines blades and towers are gradually arriving in Taiwan.
-
Financial close achieved for Taiwan’s Formosa 1 offshore wind farm
- 2018-06-08
- 發佈: ftdadmin
- Category: Newsletter
Formosa I, Taiwan’s first offshore wind farm, reached financial close on the 8th of June 2018. A financial consortium of eleven international and local Taiwanese banks as well as EKF, Denmark’s Export Credit Agency has completed this NT$18.7bn 16-year project financing. It is the first project financing in the Taiwanese offshore wind industry.
-
The Signing of the Wind Turbine Procurement Contract between Formosa I and Siemens Gamesa Working Together to Build the First Offshore Demonstration Wind Farm in Taiwan
- 2018-04-03
- 發佈: ftdadmin
- Category: Newsletter
On April 3, 2018, Formosa I (the development of which was directed by Synera (formerly known as Swancor Renewable Energy)) signed an engineering, procurement, and construction (EPC) and operation and maintenance (O&M) contract with Siemens Gamesa for 20 Formosa I Phase II 6MW wind turbines. The two companies will be working together to build Taiwan’s first offshore 128MW demonstration wind farm.